How to Switch the Date of the Project:

  1. Log into the NoteVault website.
  2. Select the project you wish to enter into from the project drop-down list.
  3. The default date will be today.
  4. Hover over the date, and arrows will appear.
  5. Click the back carrot (displayed as "<') to go back as many days as you'd like.
  6. Click the forward carrot (displayed as ">") to go forward as many days as you'd like.
  7. Your other option is to click on the "CALENDAR" button (displayed as a calendar icon) and find the exact date you wish to change the project day to.

Option 1 For Small Date Changes:

Your Other Option for a Bigger Date Jump:

Did this answer your question?